RIDIAN <br />Is <br />CONSTRUCTION SERVICE®, LLC <br />May 2, 2013 <br />Dibble Engineering <br />Attn.: Mr. Ken Snyder <br />7500 N. Dreamy Draw, Suite 200 <br />Phoenix, AZ 85020 <br />Re: Prescott Airport RSA Improvement Project <br />Request for Change Order No. 3 for Construction Management Services <br />Oridian is requesting an additive change order to our construction management services contract. Following <br />Is a breakdown of the remaining work to be completed: <br />Elliott: <br />March Pay App Review <br />16 <br />Final Pay App Review <br />16 <br />Final Quantity Verifications <br />8 <br />Engineer's Final Report <br />8 <br />Package Close -Out Docs <br />16 <br />Write Final Change Order <br />8 <br />Total <br />72 x $149.28 = $10,748.16 <br />Rov: <br />Hours Deducted From March Pay App 20 <br />Punch List Inspection 8 <br />Final inspection 8 <br />Quantity Verification 30 <br />As -Built Review 16 <br />Total 82 x $126.45 = $10,368.90 <br />Mileage / Per Diem Estimate = $600.00 <br />Less Balance remaining in contract ($64.88) <br />Total OCS Fee to Complete Project = S22,02.21111 <br />Oridian requests a change order in the amount of $21,052.18 in order to complete our contractual <br />requirements for this project. <br />Sincerely, . <br />O�RIDyIAN CONSTR ON SERVICES, LLC <br />KC Bran <br />