FINAL COST ESTIMATE FOR AWRF PHASE I PROJECT <br /> Fee Description Fee <br /> CMAR Construction GMP I $34,787,006 <br /> City Project Contingency $500,000 <br /> Generator $544,000 <br /> Engineering Design and <br /> Construction Services $5,300,000 <br /> Land Acquisition $500,000 <br /> CMAR Preconstruction Services $382,000 <br /> APS Construction Fee $30,000 <br /> Unisource Construction Fee $96,743 <br /> ADEQ Permitting Fee $75,000 <br /> City of Prescott Permitting Fee $172,675 <br /> 3rd Party CMAR Cost Model Audit I $19,900 <br /> City Staff Time $200,000 <br /> Total Cost Estimate $42,607,324 <br />